Where necessary in order to safe guard the safety of relevant persons, the responsible person must ensure that routes to emergency exits from premises and the exits themselves are kept clear at all times. All emergency lighting should be regularly checked and maintained by a competent person in accordance with the manufacturers' recommendations.
The following testing is designed to ensure the continued protection of your premises and occupants; because of the possibility of a failure of the normal lighting supply occurring shortly after a period of testing, all tests should wherever possible, be undertaken at time of least risk.
The results of all testing and any necessary corrective action should be recorded in a log book held on site, which shall be available if required for inspection by any authorised person.
The following testing schedule is in accordance with BS EN 50172:2004 / BS5266-8:2004, 7.2.3 and BS 5266-8:2004, 7.2.4. All documents should be filled in on a test record BS 5266-1:2005.
Daily;
Visually check that all maintained lamps are operating and that all system healthy indicators on Central Power Supply Systems (Central Battery Systems) are illuminated.
Check that any system fault recorded is given urgent attention and record all corrective actions in the log book provided.
Monthly;
Check all luminaires and other emergency lighting equipment is in a good condition, all lamps and light controllers are clean, undamaged and not blackened.
Briefly test all emergency lighting equipment by simulating a failure of the normal lighting supply. Check that all equipment functions correctly.
Check that once the mains supply is restored, all supply healthy indicators are again illuminated.
Annually;
A full system test should be conducted by a competent service engineer including a full rated duration test of the system. Compliance of the installation and system with the requirements of BS EN and BS standards should be considered and documented.
The following testing is designed to ensure the continued protection of your premises and occupants; because of the possibility of a failure of the normal lighting supply occurring shortly after a period of testing, all tests should wherever possible, be undertaken at time of least risk.
The results of all testing and any necessary corrective action should be recorded in a log book held on site, which shall be available if required for inspection by any authorised person.
The following testing schedule is in accordance with BS EN 50172:2004 / BS5266-8:2004, 7.2.3 and BS 5266-8:2004, 7.2.4. All documents should be filled in on a test record BS 5266-1:2005.
Daily;
Visually check that all maintained lamps are operating and that all system healthy indicators on Central Power Supply Systems (Central Battery Systems) are illuminated.
Check that any system fault recorded is given urgent attention and record all corrective actions in the log book provided.
Monthly;
Check all luminaires and other emergency lighting equipment is in a good condition, all lamps and light controllers are clean, undamaged and not blackened.
Briefly test all emergency lighting equipment by simulating a failure of the normal lighting supply. Check that all equipment functions correctly.
Check that once the mains supply is restored, all supply healthy indicators are again illuminated.
Annually;
A full system test should be conducted by a competent service engineer including a full rated duration test of the system. Compliance of the installation and system with the requirements of BS EN and BS standards should be considered and documented.
If you need to speak to a member of our team please contact our head office on 0800 1700 234
AboutA professional fire company specialising in commercial and residential fire systems with maintenance contracts to suit all businesses large and small.
Qualified and Regulated Fire Protection Services!
|
Contact |
Services |
LocationsUK WIDE
|
©
UK Fire Compliance Ltd - Registered in England - Zapped